CO129-362 - Public Offices - 1909 — Page 430

CO129 Colonial Office Hong Kong Records 理藩院香港檔案 All

8

Sea-dyke.-Base work completed to the end, as also the rows of piles driven through the base. Of the outer stone slope the greater part is finished. A ridge of stone with elay on the inside is now raised over the whole length to above high water. Of the stone thus deposited the sea-wall will be built according to the plan after the work is well settled.

Work-harbour bunding.-In progress over the whole length.

Reclaiming around the work-harbour.-Party with matter dredged from the harbour and party from junk channel, the space has now been raised by pumping the matter over the bunding to an average height of 10-5 feet.

Plant in use at Woosung Fort.--Besides the plant in use at the end of December last, one big pontoon for stone transport.

Labour. In the contractor's service the same as in December last, only increased by twelve carpenters and foreign controllers for the stone dumping :-

Day wages (native)—-

January, 7,936

February, 7,168.

March, 8835

Materials used in the work this quarter

Workable days.

19 204 22

9

These quantities are deposited as follows :--

(1)

(2.)

(3.)

Pumped on shore Dumped in mass

Total..

532,339-85 322,438.25

3,120,824.09

1,522,450-27

854,778-10

1,643,274 36

3,653.163-94 1,844,888 52

5,498,052-46

Matter pumped on shore in places as follows :—

(1)

(2.)

(8.)

At Kajow

116,664 11

-

Upper Gough

5+

Woosung Fort, reclaiming

151,801 03

Lower Gough

Total ..

263,874 71

532,539-85

2,451,464.60

669,359 49

118,664-11 2,451,464 60

151,801 03 988,234 20

3,120,824.09

3,653,163.94

Brushwood

Stakes

Laths

Ballast stove

Piles, 40 to 50 feet long

21

15, 24

lb.

58,000

lb. of 10

890

25

890

""

tous

73,059 1,137 1,208

The above by

Dredging was

(1)

(2.)

(3.)

The "Cyclops".

"Canton".

Total

299,313-83 238,026 02

532,339.85

2,305,422-30 815,401.79

3,120,824 09

2,604,736-13 1,048,427.81

3,653,163.94

Dredging work.-Contract No. 2 with the E.A.D. Company.

continued by the---

Shanghae" all the time in junk-channel.

"Rhenenia" all the time in junk-channel.

"Colonia" from the 11th January to the 14th February in the work-harbour at Woosung Fort and for the remainder of the quarter also in junk-channel.

By the suction dredger, "Canton," matter dredged from the work-harbour and from junk-channel was pumped over the harbour bunding into the space to be reclaimed from the 13th January to the 18th March, when she was removed to Kajow to pump matter on shore there.

The total dredging in the work-harbour, as previously calculated and agreed with the contract, was 119,360 cubic yards. This total was reached on the 29th January, when (from the 11th) 41,853 cubic yards was dredged. What was done after this date to the 14th February was not measured for payment.

No doubt dredging the work-harbour, at the expense of the contractor, will have to be done again afterwards. That a part of it was filled up so soon was not caused only by natural silting but mostly by matter, yet liquid, flowing out from the reclaiming over and through the bund before this was made sufficiently solid with clay for retaining the matter.

The suction dredger pump, "Cyclops," was almost all the time at work pumping up matter on shore at Lower Gough.

The quantities thus far, dredged and deposited, as measured in barges and according to the contract, are in cubic yards

(1) In this quarter;

(2) Previously;

(3) Total up to the 1st April, 1909.

Matter dumped in mass by self-discharging barges in places as follows:----

(2.)

(8.)

(1.)

Woosung Fort on zinkstuk base and

behind jetty

30,827-39

256,418-78

2,110-61

1,677-62

83,278-78

On sinkstuks, Lower Gough

Upper Gough dyke end Kajow

Mud deposit, Lower Gongh Behind dam

++

Between works' salient

Along shore salient

Between works' dyke end Above "A" crib, dyke end Between works, Upper Gough Behind par. dam, Upper Gough Between works, Kajow

--

On zinkstuks dame, Upper Gough

Total dumped

7,889-86

287,246.37 715-33 15,497-34

715-33 13,886.73 500.84 1,756 26

93,149-96

500 81 3,432-88 98,149.96 83,278-78

112,008 72

70.418-18

529,447.88 156,793-70

104,619-86 76,408 18 529,447-88

97,050-08

99,167-96 10,936-25

332,458.25

59,743 62 244,138 00 22,315-18 119,850.15

244,138-00

22,315.18 219,018 11

10,936.25

1,522,450-27

1,851,889-52

(1.)

(2.)

(3.)

By the "Colonia

55

"Rhenenia"

» Shanghai

214,031-60

331,209-63

89,0536.87

Total ..

864,778.10

1,889,861 60 1,869,080-21 884,342.55

4,643,274-36

2,108,883.20

2,200,289.00

1,193,879-42

5,498,052 46

Preparative Works. --The new mud deposit for dumping at Kajow has been completed, while the one at Upper Gough, for raising the matter enclosed to above the highest tides, may be completed before the middle of April.

Plant in Use. About the same as before. Labour.The same.

Workable Days.-This quarter seventy-two.

[2391 -6]